Installation

Adoptable and Section 104 pumping stations in Surrey

Private and adoptable package pump stations, designed to the relevant guidance, for developments and sites across Surrey where the station may later be taken on by the sewerage undertaker.

A newly installed twin packaged pumping station set into a plant-room floor, with two circular chambers, lifting chains and junction boxes.

Private stations and stations intended for adoption

A private pumping station remains the responsibility of the owner, the residents or the management company for its working life. That is the usual arrangement on a single house, and on many small developments that were never offered for adoption.

An adoptable station is designed so the sewerage undertaker can take it over and maintain it thereafter. In most of Surrey the undertaker is Thames Water. Adoption itself is usually agreed under Section 104 of the Water Industry Act 1991. Until that process is complete — and it can take years — the developer, or the management company or residents who have taken the site on, remain responsible for keeping the station working. Some stations are never adopted, and stay private.

The two are not interchangeable. A private domestic package is designed to the relevant British Standards and to Approved Document H, but it is not automatically built to an adoptable specification. If a development is intended for adoption, that needs to be decided early, because it affects the chamber, the controls, the access, the rising main and the paperwork.

The Design and Construction Guidance, and local practice

Stations intended for adoption in England should be designed to the water industry’s Design and Construction Guidance (DCG). The DCG replaced Sewers for Adoption, which you will still see named on older drawings and contracts.

Individual undertakers can also issue their own addenda, or a local practice, on top of the national guidance. Thames Water, as the undertaker for most of Surrey, publishes a Local Practice for sewerage pumping stations. On a site that sits with a different undertaker — which can happen towards the county boundary — that undertaker’s published addenda apply instead.

We design and install packaged stations for both private and adoptable schemes, and we take on servicing for either. We have not claimed a formal Thames Water, or other undertaker, accreditation or approved-installer status on this site. An adoptable installation is specified to the published guidance that applies to the site, and quoted from the drawings and the duty, not from a standard chamber size.

A maintenance contract is not a substitute for a Section 104 agreement. It is the practical way to keep the station safe and available while adoption takes its course, or for the long term if the station is to remain private.

How an adoptable pumping station project typically proceeds

The legal agreement is between the developer (or the site owner) and the undertaker. The sequence below is the practical path we see most often; the undertaker’s own process always takes precedence.

  1. Confirm, at the outset, whether the station is intended for adoption or will remain private
  2. Establish the duty: foul or surface water, incoming flow or number of properties, invert levels, discharge point and tanker access
  3. Prepare a specification that follows the DCG and the relevant undertaker’s published local practice or addenda
  4. The developer or client pursues the Section 104 agreement with the undertaker, and supplies the design information that process requires
  5. Undertakers usually advise that construction of assets intended for adoption should not start until the agreement is signed, unless they have agreed an early start
  6. We can then supply, install and commission the mechanical and electrical works, including the rising main, to the agreed specification
  7. Until adoption is complete, someone has to service the pumps, test the alarm, and know who to call if it sounds

For a quotation we need the site, whether adoption is intended, a sense of the incoming flow, invert levels and the discharge point. If you have drawings or a specification, send them; if you do not, a site visit is enough to start. After handover, the same engineers can put the station on a planned servicing contract, with tanker desilting and jetting where the wet well will need it.

Adoptable station questions

What is Section 104, in plain terms?

Section 104 of the Water Industry Act 1991 is the usual route by which a developer agrees that sewers and, where relevant, a pumping station will be adopted by the sewerage undertaker. In most of Surrey that undertaker is Thames Water. Until the agreement is completed, and in every case where a station remains private, responsibility sits with the developer or with the people who have taken the site on.

Can you install a station that is intended for adoption?

Yes. We install packaged pumping stations for private plots and for schemes intended for adoption, specified to the Design and Construction Guidance and to the undertaker’s published local practice where that applies. We do not claim a formal undertaker accreditation on this site, and we do not replace the Section 104 agreement itself — that remains between the developer or client and the undertaker.

Who services the station while it is waiting to be adopted?

The developer, management company or residents remain responsible until adoption is complete. We can put the station on a planned servicing contract in the meantime, and we will attend if the high-level alarm sounds. That keeps the asset working; it does not complete the adoption.